Pandemic to cost NASA up to $3 billion
By Jeff Foust
WASHINGTON — A NASA audit concluded that costs imposed by the COVID-19 pandemic on the agency could reach $3 billion, with several major science and exploration programs announcing for much of that cost.
A March 31 report by the NASA Office of Inspector General (OIG) stated that the agency expects that the pandemic’s effects on the agency, ranging from closed facilities to disrupted supply chains, to be nearly $3 billion. Of that, about $1.6 billion came from 30 major programs and projects, defined by NASA as those with a total cost of at least $250 million.
“Although NASA managers include schedule margin in program and project plans to address unforeseen circumstances, in many instances the margins were not sufficient to absorb the impact of the pandemic,” the OIG report stated. It added the full cost accounting of the pandemic won’t be possible “until after the COVID-19 emergency has subsided.”
The project with the largest cost increase in the report is the Nancy Grace Roman Space Telescope, formerly known as the Wide-Field Infrared Survey Telescope (WFIRST). It reported $3 million in costs because of the pandemic in fiscal year 2020, but estimates nearly $400 million in additional impacts in future years. The mission has a lifecycle cost of $3.9 billion.
“Subcontractors working on the Roman Space Telescope have been significantly impacted, resulting in fewer bids on proposed work, longer delivery times, and parts delays to complete assemblies,” the report stated. “This, in turn, has impacted contractors and affected the schedule for higher assembly and testing.”
NASA officials previously said Roman was particularly hard hit because the pandemic came at the peak of its projected spending, just as it passed its Key Decision Point C review in early March 2020. That review approved plans to move into full-scale development of the space telescope.
“COVID has had a measurable impact on the Roman Space Telescope,” said Paul Hertz, director of NASA’s astrophysics division, said at a March 25 meeting of the Committee on Astronomy and Astrophysics of the National Academies’ Space Studies Board. “COVID hit at exactly the worst possible time for a mission.”
Hertz didn’t quantify the cost and schedule effects of the pandemic on Roman, although he previously said the launch would likely slip six months, a delay also noted in the OIG report. Once those impacts were independently verified, “we will be going through a process of resetting the Roman schedule and the cost that goes with that reset.”
The OIG report stated that, given the known effects of the pandemic, “officials already anticipate needing additional funding for [fiscal year] 2022” for Roman.
The Space Launch System had the second-highest cost increase in terms of overall dollars, at $363 million, of which $8 million was in fiscal year 2020 and $355 million in fiscal years 2021 through 2023. A three-month delay in the first SLS mission, Artemis 1, along with “rephrasing production” each accounted for about one-third of the costs. The rest came from “surge costs” to compress schedules as well as the costs of facility shutdowns.
The Orion spacecraft suffered $146 million in costs, including $5 million in fiscal year 2020 and $66 million in fiscal year 2021. Because the Orion spacecraft for the Artemis 1 mission was nearly complete at the time the pandemic hit, the largest effects were on the Orion spacecraft for the Artemis 2 and 3 missions, both still in production. Those problems extended to Europe, with delays in the production of the European Service Module for the Artemis 2 Orion.
The James Webb Space Telescope will see its cost increase by $100 million because of the delay in its launch from March to October of this year. That increase, though, will be contained within the $8.8 billion cost cap for the mission using existing budget reserves.
Two other science missions in development, Europa Clipper and the Plankton, Aerosol, Cloud and ocean Ecosystem (PACE), reported costs increases of $97 million and $89.2 million, respectively. PACE, whose cost increases account for about 10% of its estimated total cost, will also see its launch slip by nine months.
Many other major projects and programs, though, saw far lower cost increases. The commercial crew program experienced $2.2 million in cost increases in 2020 and $2.3 million projected for future years. The 2020 increase came from the use of NASA aircraft for mission-essential travel during the pandemic and “socially distanced lodging” for astronauts and other personnel ahead of the Demo-2 and Crew-1 launches in May and November of 2020, respectively.
How NASA will cover those costs is not certain. The agency received just $60 million in the Coronavirus Aid, Relief, and Economic Security (CARES) Act in March 2020, which the agency is using for pandemic-related costs ranging from enhanced information technology infrastructure to personal protective equipment. Hertz, in recent presentations, noted that overruns in one part of NASA’s astrophysics portfolio, such as the flagship missions JWST and Roman, would not be paid out money in other parts of the portfolio, like smaller missions or research funding.
The costs estimates included in the report, OIG added, are unlikely to be final figures. “Due to the continued uncertainties around the COVID-19 pandemic, NASA will likely continue to experience impacts to its major programs and projects.”
April 1, 2021 at 05:00AM
via SpaceNews read more...
Post a Comment